Enemalta reportd that at 6:51am, a third party private contractor working on road works in Marsa, hit an underground 11kV Enemalta cable which resulted in the suspension of supply in parts of ─Žamrun, Marsa and Santa Venera.

Enemalta said its employees were immediately on site to identify the extent of the damage.

The fault is currently being isolated and repair works were expected to start shortly after.

Power is expected to be restored to all localities by 10:00am.